October 2017 Update!

  • The Playground Removal has been tabled until we have more legal information and/or options.
  • Landscape Update – Brightview has completed the pruning of all bushes and shrubs. The final bed edging is in process. The pond cleanup has been completed. The Ash tree removal and replacement on Torch has been completed. As for Cantera, the Ash tree removal and replacement is scheduled to begin the week of October 9. Twenty four trees will be removed and 16 replaced. The same amount is planned for 2018 at $32,000. The new front entry stones have been installed and irrigation heads were replaced. Fall flowers will be planted in the entry and also the median the week of October 2.
  • Property Committee Update – Fifty units were fixed with rotten wood this year. This fall, 32 units will have their fireplace vents replaced, and 22 buildings will have their North side power washed.
  • Remember, if you have big items to be thrown away, you need to contact Groot ahead of time!
  • There has been a lot of discussion about the hearing on the development of the 28 acre property to the southwest of the Cantera pond. Planned development includes about 60 three-story town homes and a 4 story building with 364 apartments. Retail space with a high-end grocery store are also planned. The Planning Commission has agreed to meet with Cantera Village to answer questions about this development. Please contact Associa if you are interested in attending this meeting! We will post the date/time/place for this meeting as soon as it is set.
  • Happy Halloween! If you are participating in trick or treating, please put your porch light on so families know you are taking part.
  • Annual meeting is Thursday, November 16 where board elections will take place. We need a quorum, so please attend!

Any questions, comments, or problems, please contact

Associa Chicagoland, 847.490.3833 or

www.associachicagoland.com

Advertisements

September 2017 Update!

  • Next Cantera Board meeting is Thursday, September 28th at 7pm at Warrenville City Hall. Please join us!
  • We will have the final discussion/vote on tearing down the playground at this meeting.
  • A hearing on the development of the 28 acre property to the southwest of the Cantera pond is set for September 7th at the Village Hall. Planned development includes about 60 three story town homes and a 4 story building with 364 apartments. Retail space with a high end grocery store are also planned.
  • Landscaping: The stone walls and landscaping at the Winfield Road entrance will be replaced this month. This is work approved in November and included in our 2017 budget.
    Miscellaneous plant replacements will be taking place this month to fill in for plants that have died. This is also in our 2017 budget.
    23 ash trees affected by Emerald Ash Borer (EAB) on our property will be removed in September. We will be planting 20 trees in their place per our landscaping plan. This work is fully funded by our reserves. This is in addition to the trees removed on Torch Parkway. Replacement trees will be planted this month in all areas.
  • Property: The 2017 rotten wood project is complete. We are continuing our effort on Work Orders as they are received.
    We are planning on a concrete repair project this fall to capture several current concrete work orders.

Any questions, comments, or problems, please contact

Associa Chicagoland, 847.490.3833 or

www.associachicagoland.com

August 2017 Update!

  • Landscaping Update: The selected reeds in the pond have been treated in order to kill them. Once dead, these reeds will be removed from the pond.
  • Property Committee Update: The rotten wood project is underway. If you have rotten wood at your unit, please call it in to Associa to make sure it is addressed this year.
  • Board Update: We are starting the 2018 operating budget process. The third party reviewer of the reserve account and projected expenses is expecting to have a draft report to the Board this month.
  • School is back in session this month, please watch out for kids and buses!

Any questions, comments, or problems, please contact

Associa Chicagoland, 847.490.3833 or

www.associachicagoland.com

July 2017 Update!

  • Landscape Update: Brightview has completed the summer flowers at the entry way, shrub pruning, restoration work at two locations, arborvitae removal, pruning around the AC units, seeding repairs two times because of excess rain, and new mulch! Let’s allow our professional landscapers to beautify our neighborhood, no modifications please!
  • Property Committee Update: We are still working on reducing the number of open work orders! Rotten wood work will begin on over 50 units during the second week of July.
  • Welcome Committee: Come out and enjoy a Kane County Cougars game on Thursday, July 27 th at 6:30pm. $19 for ticket and included $10 in Ozzie bucks. It is also a thirsty Thursday night so beer will be $1. It’s Wayne’s World night, so the first 1500 guests will receive a Bobblehead! Give money to Sue Fox or Marsha Nolan.
  • The playground will be demolished soon because of liability issues.
  • Reminder to all residents: There is a no rental policy in this neighborhood. If you are found to be renting, the fine is $50 per day.

Any questions, comments, or problems, please contact

Associa Chicagoland, 847.490.3833 or

www.associachicagoland.com

 

June 2017 Update!

  • Garbage and Recycle: As detailed last month, we request that all homeowners adhere to the Association Rules and Regulations by not putting their garbage and recycle out before dusk on the evening preceding the day of collection.  We again appeal for garbage and recycle not to be left outside before 7am on the day of collection if the weather is windy and/or stormy. On Thursday May 18th garbage was blown across many areas of the subdivision due to stormy overnight weather. If there are trash and recyclables blowing around, please pick them up!
  • Landscaping Update: Budgeted Arborvitae replacement has been delayed due to wet weather and will start this month. Our front entryways will be dramatically improved!
  • Property Committee Update: The already budgeted rotten wood project has also been delayed because of all the rain and will be kicking off in June. Another focus for June? Completing old work orders!
  • Board Update: The complex reserve budget and project scope are being reviewed this month to ensure that we are tracking all appropriate project and our funding for those projects are in place.